FRIDAY, FEBRUARY 27, 2026

  • Total pipe installed ~16,800 ft of 64,000 ft = ~26%

 

  • Van Buren Street from Butternut to 160th Avenue is closed and from 160th to 152nd Avenue is closed.
  • K&R crossed Whitetail Ct with pipeline this week.
  • Approximately 4,000′ of pipe has been installed on this project.
  • K&R continues to lay pipe in Van Buren progressing east from 160th. They are approximately 400′ west of Whitetail Ct.

 

  • Van Buren Street from US-31 to 120th Avenue is closed.
  • K&R crossed 128th Avenue with pipeline this week and is restoring the intersection.
  • Approximately 3,800′ of pipe has been installed on this project.
  • Next week, K&R will continue to lay pipe in Van Buren progressing east. A small section of pipe just east of 128th Avenue will be skipped until additional materials arrive. This section of pipe will be installed later.

 

  • New Holland Street from 104th Avenue to 96th Avenue is closed.
  • Ric-Man continued pipe installation in New Holland Street. Approximately 900′ of pipe in New Holland Street remains to be installed.
Contact a Location
Learn About Us
View Our Services
Facebook-f Linkedin Youtube Instagram

© 2026 Prein&Newhof, All Rights Reserved

  • Plan Room
  • Lab Results
  • Construction Updates
  • Survey Request