Van Buren Street from Butternut to 136th Avenue is closed.
The intersection of 160th and Van Buren is closed.
Pipe has been installed through the intersection. Next week, K&R will install a large vault and valve adjacent to the intersection and install culverts beneath Van Buren between 160th and 152nd.
Near 144th, K&R’s crew began pipe installation and laid approximately 400′. Pipe laying will continue eastward next week.
Van Buren Street from US-31 to 120th Avenue is closed.
Work on various items continued this week with the intent to begin road building soon. This site will not see a lot of activity next week.
New Holland Street from 104th Avenue to 96th Avenue is closed.
Work on various pipe appurtenances will continue next week with work generally progressing from south to north.