Work Completed Last Week:

  • Decorative concrete poured on East Main Street.
  • Planter boxes poured on the east side of State Street.
  • Completed pouring all concrete light pole bases.
  • Conduit and irrigation installed west of State Street.
  • Continued installing sidewalk ramps at the intersection of State and Main

Anticipated Work This Week:

  • Continue installing decorative concrete sidewalk west of State Street.
  • Continue pouring concrete roadway in State Street and E. Main Street.
  • Complete installation of planter boxes.
  • Install asphalt pavement on Main Street, east of State Street.