Progress Report
- Broadway: All water mains are now installed, and all water customers are connected to the new water mains.
- Broadway: Crews are working on replacing the sanitary sewer main in Broadway between Temple and Waalkes.
- Broadway: Crews continue to install underdrain and road gravel base between 6th and Park Streets
- Delano Avenue: Underground utility work is complete in many alleys and in Howden and Wood Street intersections.
- Sanford Street: New water main pipe has been installed from Norton to Oakwood and in Maplewood between Sanford and Jefferson.
- Norton Avenue: A new 18-inch valve was successfully installed on a major water transmission main near Peck Street
The posted detour for Broadway Avenue is Glade Street to Summit Avenue to Peck Street back to Broadway.
The posted detour for Delano Avenue is Reynolds Street to Hackley Avenue to Getty Street
The posted detour for Sanford Street is Oakwood Avenue to 5th Street to Norton Avenue
Upcoming Work Planned for Next Few Weeks:
- Broadway: Crews should complete the remaining sanitary and storm sewer replacement work this upcoming week.
- Broadway: Road reconstruction, along with sidewalks, curb and gutter is ongoing through the entire corridor.
- Water service replacements are happening all over the City as part of the Lead Service Line Replacement program
- Delano: Water main connections will take place at Jarman this week and work will move over to Ray Street intersection
- Delano: Intersections at alleys and at Howden and Wood will be rebuilt with gravel and concrete curb and gutter. Asphalt road restoration is likely in some areas before Independence Day
- Sanford: Water services will be replaced to the new water mains. New storm drains will be installed/replaced at the same time.
- Oakwood: Water main connection work will begin next week at Cleveland and Glade and then progress down Oakwood between Glade and Mona. Pavement removals will begin next week.
- Getty Tank: Repainting will begin with a very large containment shroud being installed for protection while the old paint is blasted off before the tank can be repainted
New 18-inch transmission main valve installed in Norton Avenue near Peck Street:
Broadway: Gravel road base is installed and some sidewalks have been installed. Looking west at 6th Street:
Broadway: Gravel road base is installed and some sidewalks have been installed. Looking east at 6th Street:
Old storm drain pipe removed in Maplewood between Sanford and Jefferson:
New storm drain pipe ready for installation after the water main is installed in Sanford, north of Maplewood: