Progress Report
- Broadway: The first asphalt was paved yesterday between 5th and 9th Streets!
- Broadway: All underground utility work is complete. Concrete curb and gutter, sidewalks, driveway approaches and sidewalk ramps are done from 5th to 9th and between Temple and Glade. Lawn restoration has begun already in most places along the route.
- Delano Avenue: Utility work remains at the following intersections: Jarman, Ray and Riordan. Paving has begun on Delano at alley intersections with the first course.
- Sanford Street: All underground utility work is completed. A few water services remain to be connected to the new water main.
- Oakwood Avenue: Water main connections are taking place along Oakwood between Glade and Mona. New water main is installed in Cleveland between Glade and the first ally east.
- Amsterdam Avenue: Pavement removal has begun and water main removal has begun
- Getty Tank: The tank had rigging installed for the shrouding for the old paint removal. The interior has been blasted and is being prepped for new coatings
- Lead Service Lines continue to be replaced throughout the City
The posted detour for Broadway Avenue is Glade Street to Summit Avenue to Peck Street back to Broadway.
The posted detour for Delano Avenue is Reynolds Street to Hackley Avenue to Getty Street
The posted detour for Sanford Street is Oakwood Avenue to 5th Street to Norton Avenue
Upcoming Work Planned for Next Few Weeks:
- Broadway: Concrete work will be completed between 9th and Temple in the next week. Manhole structures will be raised in the new asphalt section between 5th and 9th. Gravel grading will take place between 9th and Glade in preparation of the next round of paving.
- Water service replacements are happening all over the City as part of the Lead Service Line Replacement program
- Delano: Water main connections will take place at Ray, Jarman and Riordan. The last few intersections will be rebuilt and concrete curb and gutter and sidewalk ramps will be poured next week at nearly all the remaining intersections.
- Sanford: The old water main will be taken out of service on Monday, July 13. The last few water services will be connected and road building will begin next week with cutting the sand for gravel road base to be installed
- Oakwood: Water main connections will continue to occur and residents may have temporary water disruptions in the area between Norton and Broadway and Glade and Mona while these water main connections are taking place.
- Amsterdam: Water main installation may begin later next week after additional pavement removals
- Getty Tank: Once the containment shroud is installed, blasting will begin removing the old paint and new painting may begin on the tank