MONDAY, JULY 27, 2026

  • Van Buren Street from Butternut to US-31 is closed.
  • The intersection of Van Buren Street and 136th Avenue is closed and is scheduled to be paved on July 30 and reopened on July 31.
  • 144th Avenue, south of Van Buren, is scheduled to be closed starting July 31 for pipeline installation.
  • Restoration work continued between 160th and 152nd. Road reconstruction between 144th Avenue and 136th Avenue will begin soon.
  • Pipe laying between 152nd and 144th Avenue has progressed to the 144th Avenue crossing. The 144th Avenue crossing is scheduled to begin after the road closing on July 31. The crossing will take approximately two weeks.
  • Pipe laying between 144th and 136th Avenue has progressed through the 136th Avenue intersection.
  • This week, both pipe crews will be working primarily on hydrants, air valve assemblies, and other appurtenances along the pipeline.
  • Work inside the pipe continues.

 

  • Van Buren Street from US-31 to 120th Avenue is closed.
  • Preparations will continue this week for the tunneling beneath US-31 and the Railroad.
  • Pipe laying is expected to resume near the end of July.

 

  • New Holland Street from 104th Avenue to 96th Avenue is closed.
  • Work continued on restoration within New Holland Street.
  • Work in New Holland Street will continue this week in preparation for paving.
Contact a Location
Learn About Us
View Our Services
Facebook-f Linkedin Youtube Instagram

© 2026 Prein&Newhof, All Rights Reserved

  • Plan Room
  • Lab Results
  • Construction Updates
  • Survey Request