Work Completed 

  • Generator set and wired
  • Pump bases poured
  • Valves and piping painted
  • Electrical conduit and wiring continued

Upcoming Work:

  • Set pumps and finish installing and testing final valves and piping
  • Install generator gas piping
  • Complete electrical and instrumentation wiring
  • Complete PLC and SCADA programming
  • Generator startup scheduled for August 3-4
  • MCC startup scheduled for August 10-11
  • Live lift station startup scheduled for August 12
    • Before live startup, flows will be diverted through the new 20-inch force main to West Randall Lift Station