Work Completed
- Generator set and wired
- Pump bases poured
- Valves and piping painted
- Electrical conduit and wiring continued
Upcoming Work:
- Set pumps and finish installing and testing final valves and piping
- Install generator gas piping
- Complete electrical and instrumentation wiring
- Complete PLC and SCADA programming
- Generator startup scheduled for August 3-4
- MCC startup scheduled for August 10-11
- Live lift station startup scheduled for August 12
- Before live startup, flows will be diverted through the new 20-inch force main to West Randall Lift Station