Progress Report:

On Cannonsburg Road, work is continuing on the pathway project. Terracon has completed subgrade grading for all of the path. Progress is still continuing to be made on leveling and compacting the western end of the corridor and gravel continues to be placed near the eastern end of the corridor, which will carry into next week.

Upcoming Work:

Gravel placement will continue along the path throughout next week. In addition, the leveling and compacting of subgrade along certain areas of the path will also continue. Integrity Landscaping is expected to mobilize on site at the beginning of next week to begin construction on the retaining wall near the intersection of Bear Creek Trail and Cannonsburg Road. Riverworks Construction will also mobilize on site to begin construction of the boardwalk near the Bear Creek overpass.