Progress Report:
Riverworks Construction is closing in on completion of the boardwalk near Bear Creek and expects to wrap up that section by mid next week. Simultaneously, a second Riverworks crew has been active near the Pettis Road intersection, making progress on pile driving for the large boardwalk there.
Upcoming Work:
Once the Bear Creek boardwalk is finished mid-week, the crew will transition to join construction efforts at the Pettis intersection boardwalk. Pile driving at that location will continue into next week as that structure takes shape.