Progress Report:

The boardwalk near Bear Creek is nearly complete! Remaining work is limited to railing installation, with the crew anticipating full completion early next week. At the Pettis Road intersection, pile driving is continuing and is expected to wrap up by mid next week. Installation of the boardwalk’s support members has also begun at that location.

Upcoming Work:

Next week the Bear Creek boardwalk is expected to reach completion, and pile driving at the Pettis Road boardwalk should be finished by mid-week, allowing structural work there to continue moving forward.