Progress Report:
K&R continues to lay 21-inch gravity sewer along 120th Ave heading north towards James Street.
Upcoming Work:
The closure of the James Street and 120th Ave intersection is scheduled for MONDAY, SEPTEMBER 21. See the map above for the respective detour routes. Local traffic will have access to their property for the duration of the closure.
Local traffic will have access as follows:
- 120th Ave from Lakewood to James will have access from the south via Lakewood Blvd. 120th Ave from Lakewood to James will continue to have one northbound lane open from Lakewood Blvd to Garden Ave. Local Traffic will enter 120th from the south at Lakewood Blvd, head north on 120th and exit via Garden Ave back to Lakewood Blvd. Local traffic south of the James and 120th Intersection and north of Garden Ave will have access north of Garden Ave with two way traffic to enter in and out. The two way traffic zone will also be redirected to Garden Ave when exiting.
- 120th Ave from Riley to James will have access from the north via Riley/Felch.
- James street from US31 to 120th will have access from the west via US-31.
- James Street from 112th to 120th will have access from the east via 112th.