Van Buren – Butternut to US-31
- Van Buren from Butternut to US-31 is closed.
- Road building between 140th and 136th continued. Paving has been rescheduled to September 22 from 140th through 136th Ave.
- Restoration between 152nd and 144th continues. Next week, the area will be seeded.
164th – New Holland to Van Buren
- 164th Ave is closed between New Holland and Van Buren.
- Transmission main installation began on the south end of 164th Avenue, progressing north. Approximately 800 feet of pipe was installed this week.
Van Buren – US-31 to 96th Avenue
- Van Buren from US-31 to 120th Ave is closed.
- The Van Buren/120th Avenue intersection was closed today and will stay closed for approximately two weeks.
- The tunneling operation beneath US-31 has been suspended for the time being.
- Transmission main installation began just west of 120th Avenue. The 120th Avenue crossing will take place Monday, September 21.
New Holland – 104th to 96th & Easement
- Van Buren Street between 104th and 96th Avenue is closed.
- Pavement striping and mailbox replacement was completed in New Holland Street.
- Work continued on pipe appurtenances adjacent to Van Buren Street and Barry Street.
- Next week, preparations for final acceptance testing will continue and the pipe will be filled. Acceptance testing is scheduled for late next week and the following week.