Work Completed:
  • Remaining piping between Bypass Control Structure and Control Structure B installed
  • Piping from Pond 4 to Control Structure B installed
  • Control Structure B gate valves installed
  • Control Structure A installed
  • Pond 4 liner repaired
  • Concrete pads poured over clay liner in Ponds 3 and 4
  • Progress Map
Upcoming Work:
  • Install piping from Pond 1 to Control Structures A and B
  • Partially install piping from Control Structure A to Pond 2
  • Connect existing influent force main to Control Structure A
  • Begin transfer of water from Pond 2 to Ponds 3 and 4, discharge from Pond