Van Buren – Butternut to US-31
- Van Buren from Butternut to US-31 is closed.
- **The intersection of Van Buren, Butternut, and 164th is closed.**
- The final layer of asphalt from 144th to east of 136th has been paved.
- Temporary asphalt was placed on Van Buren near US-31 where the tunneling work was suspended.
- Pavement markings were placed.
- The restoration crew continues to rebuild ditches; replace mailboxes; and topsoil, seed, and mulch areas disturbed by construction.
164th – New Holland to Van Buren
- 164th Ave is closed between New Holland and Van Buren.
- Transmission main installation in 164th Avenue has reached Butternut. The Butternut crossing will take place today through early next week. Paving is tentatively scheduled for the week of November 9.
- Welding and joint grouting inside the pipe along 164th Ave pipeline continued this week.
- Road building along 164th Avenue began this week. Paving is tentatively scheduled for the week of November 9.
Van Buren – US-31 to 96th Avenue
- Van Buren from US-31 to 112th Ave is closed.
- The intersection of Van Buren and 112th Ave is scheduled to close in the coming weeks.
- Transmission main installation continues easterly and is approaching 112th Avenue.
- Road building continues intermittently.
New Holland – 104th to 96th & Easement
- Van Buren Street between 104th and 96th Avenue is closed.
- Acceptance testing is underway and will continue next week.
- Restoration work within the SW of Blendon Drain was completed.
- Restoration work within the Bosch & Hulst Drainsis expected to begin this week.
Drinking Water Plant – Surge Suppression System
- Basement slab and walls have been poured and forms removed.
- Exterior surface has been prepped and damp proofing is underway.