Progress Report
- Amsterdam Avenue: Road gravel base material has been installed and is being shaped and prepared for asphalt next week. Topsoil areas were hydroseeded.
- Norton: Storm drain lines in the Seminole and Norton intersection have been installed. Several water services were replaced.
- Lead Service Lines: Roughly 85 lead water services were removed from the system in Waalkes and Howden.
Upcoming Work Planned for the Next Few Weeks:
- Amsterdam: Asphalt paving is scheduled for mid-week next week – weather permitting. Structures will be adjusted to the new pavement elevation after that.
- Norton: Continue water service work in Seminole and complete the new storm drain installation at Norton and Seminole. More water services and water main connections will take place in Norton between 5th and Jefferson.