Van Buren – Butternut to US-31
- Van Buren from Butternut to 160th Ave is closed.
- Van Buren from 160th Ave to US-31 will be reopened to traffic by the end of the day.
- The intersection of Van Buren, Butternut, and 164th Ave is closed.
- The restoration crew has been preparing the area for winter and addressing some punchlist items.
- The Butternut intersection was prepped for paving. Paving is tentatively scheduled for next week 11/9 and 11/12.
164th Ave – New Holland to Van Buren
- 164th Ave is closed between New Holland and Van Buren.
- Restoration and road building continued on 164th Avenue. Paving is tentatively scheduled for next week 11/9, 11/10, and 11/12.
Van Buren – US-31 to 96th Ave
- Van Buren from US-31 to 96th Ave is closed.
- The intersection of Van Buren and 112th Ave remains closed.
- Transmission main installation crossed 112th Avenue. Next week, the pipeline crew will move west and begin laying the remaining transmission main between 120th Ave and 112th Avenue.
- A second pipeline crew began building transmission main east of 108th Ave toward 104th Avenue. The 104th Ave intersection will be closed after the 112th Ave intersection is reopened.
- Road building continued between 124th Ave and 120th Avenue.
- The 112th Ave intersection is tentatively scheduled to be paved on 11/10.
- Work inside the pipeline continues.
- A large box culvert was installed between 104th Ave and 96th Avenue.
Easement
- Acceptance testing of the transmission main is completed.
- Restoration work within the Bosch & Hulst Drain continued and is expected to finish next week.
- Site cleanup and punch list work will continue next week.
Drinking Water Plant – Surge Suppression System
- Backfilling continued
- The first section of Operating Level footings were poured and stripped. The remaining footings were formed and will be poured today.
- Next, the Operating Level foundation walls will be prepped and poured.