Georgetown Charter Township - Baldwin Street Transmission Main

Important Information

Georgetown Charter Township will be constructing a new 24-inch water transmission main in Baldwin Street from where the previous phase ended 600 feet east of 48th Ave to the storage tanks 1200 feet east of 36th Avenue.

The transmission main project is anticipated to occur in five stages beginning around early April 2027 and working through November 2027. Certain stages of construction will require Baldwin Street to be closed to all through traffic, and other stages will necessitate partial closures and lane shifts.

Construction Scope

Roadwork:
The contractor will remove the road surface on the north side of the road ahead of water main construction. The contractor will also repave the top layer of asphalt on the south side of the road when they restore the road.

Water Main:
The 24-inch water transmission main will be constructed 10 feet north of the centerline of the road, generally from the west to the east, from about 600 feet east of 48th Avenue to about 1,200 feet east of 36th Avenue. The water main will connect to existing water mains at 40th Avenue and at the storage tanks.

Access & Traffic

Stage 1: Baldwin Street will be fully closed from east of Fox Meadow Drive to east of 42nd Avenue. The intersection at Baldwin Street and 42nd Avenue will be closed. The proposed detour will utilize 48th Avenue, Bauer Road, and 36th Avenue.
Stage 1 Detour Map

Stage 2: Baldwin Street will be fully closed from east of 42nd Avenue to east of 40th Avenue. The intersection at Baldwin Street and 40th Avenue will be closed. The proposed detour will utilize 48th Avenue, Bauer Road, 36th Avenue, and Port Sheldon Street.
Stage 2 Detour Map

Stage 3: Baldwin Street will partially closed east of 40th Ave, with lane shift tapers extending to the east and west. There will be one lane of traffic each direction on the south half of the road. Left turns onto 36th Avenue from Baldwin Street will not be allowed. Traffic seeking to turn left onto 36th Avenue must either use 42nd Avenue and Bauer Road or 28th Avenue and Port Sheldon Street.
Stage 3 Detour Map

Stage 4: The intersection at Baldwin Street and 36th Avenue will be fully closed to traffic from all sides. The proposed detour routes will utilize 48th Avenue, Bauer Road, 28th Avenue, and Port Sheldon Street.
Stage 4 Detour Map

Stage 5: Baldwin Street will be partially closed east of 36th Avenue, with lane shift tapers extending to the east and west. There will be one lane of traffic each direction on the south half of the road. Left turns onto 36th Avenue from Baldwin Street will not be allowed. Traffic seeking to turn left onto 36th Avenue must either use 42nd Avenue and Bauer Road or 28th Avenue and Port Sheldon Street.
Stage 5 Detour Map

Mail:
Mail, Amazon, and other deliveries will continue to have access for deliveries.

Garbage Pickup:
Standard waste service will continue. On pick-up days, please place your bins in an accessible location clear of construction.

Driveways:
You may temporarily lose driveway access when work is directly in front of your property, but you will not be left without access overnight

Contact

P&N Engineer:
Lucas Timmer, PE
Project Manager
616-588-9023

Joel Bylsma, EIT
Project Engineer
616-432-6693

P&N Construction Observer:
Max Hazen
616-928-1591

Contractor:
Kamminga & Roodvoets, Inc.
Chad Heyboer, Superintendent
Tim Brinks, Project Manager
(616) 949-0800

Georgetown Charter Township
Joel Hanenburg
616-226-6005