Cannon Township - Belding Road Sewer Replacement - Grass Lake Lift Station to Myers Lake Ave

Important Information

Cannon and Courtland Townships are replacing a 12-inch shared trunk sewer along the south side of Belding Road with a 21-inch PVC pipeline. The work will take place between the Grass Lake Lift Station (6208 Belding Rd) and Myers Lake Avenue from June through September 2026. The existing sanitary sewer is being replaced because it is nearing the end of its useful life.

Access/Traffic:

Construction will require a lane shift on Belding Road. Eastbound traffic will be sifted into the center turn lane through the construction zone for the duration of the project. Road closures and detour routes of Egypt Valley Ave. and Myers Lake Ave. will be required to install the new sewer across these intersections. Homeowners will have limited driveway access during the time the sewer is installed across it, but access will be available at the end of each work day.

Mail:

The Contractor will work with residents to maintain mail and package delivery throughout construction.

Garbage Pickup:

The Contractor will work with residents to maintain garbage disposal throughout construction.

Contact

P&N Engineer
Jeremy Kamp, PE
616-364-8491

P&N Construction Observer
Prein&Newhof will have staff on site during construction.

Contractor
Dean’s Excavating
Nate Wall
616-636-5524

Cannon Township
616-874-6966

powered by Advanced iFrame

Construction is now complete and traffic patterns have been returned to normal. Dean’s Excavating does have some outstanding punch list work to complete. Dean’s Excavating will be off site for the next two weeks and return the week of November 16 to complete sewer testing and any outstanding work. This work will be completed under a shoulder closure.

Myers Lake Avenue was opened to traffic on Friday last week.

Sanitary sewer construction wrapped up last week and Dean’s has switched gears to road reconstruction between Myers Lake and Silver Maple. The remainder of the shoulder and driveway paving has been scheduled for this week Wednesday. Dean’s will then work on final restoration and punch list items over the course of the next week.

 

Myers Lake Avenue continues to be closed between Belding Road and Cannonsburg Road. The Cannon Township Center can be accessed from Belding Road as the Myers Lake Avenue entrance is completely closed.

Dean’s is making good progress installing the new sanitary sewer through the intersection. Today, Thursday, Dean’s will make the connection to the existing sewer on the east side of Myers Lake. Sanitary sewer work is expected to be completed early next week.

Roadside restoration work was completed this week between Egypt Valley Avenue and Silver Maple Lane.

Dean’s has concrete work scheduled for next week Monday and paving is scheduled to be completed the second half of next week weather permitting. Once the intersection is paved the road closure will be removed.

Starting Monday, October 12, Myers Lake Avenue will be closed south of Belding Road while sanitary sewer construction is completed through the intersection.

Traffic will be detoured east to Ramsdell Avenue.

The closure is expected to last approximately two weeks, with the intersection scheduled to reopen by Friday, October 23.

Dean’s Excavating will install the new 21-inch sanitary sewer main approximately 15 feet deep across the intersection while removing the existing pipeline. A pump and haul operation will be required for one day near the end of next week to allow Dean’s Excavating to connect the new sewer to the existing sewer. The pump and haul operation will require semi tankers to be staged along the east shoulder of Myers Lake Avenue, north of Belding Road, and will close off the south driveway of Huntington Bank for one day.

Thank you for your patience and cooperation as Cannon Township completes this important infrastructure improvement.

Progress Report:

Northland Drive was opened ahead of schedule this week. Dean’s Excavating has been doing some sewer testing this week under the shoulder closure.

Next week, the lane shift along Belding Road will be put back in place on Monday morning. Dean’s will continue sanitary sewer replacement up to Myers Lake. Myers Lake will be closed to thru traffic end of next week or beginning of the following week to allow the sanitary sewer to be replaced through the intersection. Myers Lake traffic will be detoured and the closure is expected to last for around 1 week.

Sanitary sewer construction is scheduled to wrap up by middle of October with project restoration scheduled to be completed by the end of October.

Progress Report:

Northland Drive will be closed between Belding Road and West River Drive starting on Friday, September 25. The closure is expected to last until the morning of Monday, October 5.

Why does this matter for the Belding Road Sewer Replacement project? Because the detour for the Northland Drive closure will be Cannonsburg Road to Myers Lake Avenue to Belding Road. More information on the Northland pedestrian crossing project can be found here: https://www.preinnewhof.com/construction-projects/northland-pedestrian-crossing/

In anticipation of heavier traffic volumes through the work zone next week, Dean’s Excavating will take a break from installing new sanitary sewer. Dean’s plans to install sewer through Thursday this week and then remove the lane shift on Friday so that only the eastbound shoulder is closed. Base course paving is also scheduled for Thursday this week between Egypt Valley Avenue and Silver Maple Lane. The final top course of asphalt won’t be placed until the end of the project so that it can be placed all at one time.

Next week, Dean’s will work on some sewer testing and project clean up under the shoulder closure.

Upcoming Work:

After the Northland Drive closure is completed, Dean’s will put the lane shift back along Belding Road and close Myers Lake Avenue so that the new sewer can be installed across the intersection. Dean’s anticipates about three weeks of work remain after the Northland Drive closure. The project is scheduled to wrap up before the end of October.

Progress Report:

  • Base course paving from the lift station thru Egypt Valley Avenue has been completed. Top course paving, the last 1.5″ of asphalt, will be done for the whole project at the end.
  • Dean’s continues to replace the sewer and bypass pump existing sewer flows around the work area. Current progress is a few hundred feet west of Old Town Road.
  • Dean’s continues to rebuild the road behind the sewer crew east of Egypt Valley Avenue.

Upcoming Work:

Pending weather delays, sewer work is expected to wrap up in early October with shoulder restoration completed by the second half of October.

Progress Report:

Dean’s continues to progress east with new sanitary sewer installation.

Concrete curbs were replaced at Egypt Valley last week as well as concrete sidewalk around the lift station.

Dean’s is working on shoulder restoration between the lift station and Egypt Valley in preparation for paving.

Upcoming Work:

Myers Lake will be closed for one week to install the new sewer through the intersection in the second half of September. The closure of Myers Lake is being coordinated closely with other projects and detour routes in the area.

Dean’s continues to make progress on the sanitary sewer replacement along Belding Road. The new sewer was installed through the Egypt Valley intersection this week. Next week concrete curb will be replaced at the Egypt Valley intersection and Dean’s will work on shoulder restoration between the lift station and Egypt Valley. Sanitary sewer construction will continue east of Egypt Valley.

Dean’s continues to progress east with the new 21-inch PVC sanitary sewer. Dean’s had Diversified Dewatering install a groundwater dewatering system end of this week. The existing soils have changed to mostly sand which allows for easier groundwater dewatering. Prior to this week the existing soils were primarily clay at the bottom of the trench which do not allow for a traditional dewatering system to be installed. The dewatering system should help speed up the installation of the pipe up toward Egypt Valley.

Sewer installation will continue next week towards Egypt Valley.