- The lift station was started up on August 17. Flow was diverted to West Randall Lift Station on August 18, and the station was considered substantially complete on August 19 after Windemuller corrected some controls and SCADA issues. The bypass pumps will be removed early next week.
- We are compiling a punch list and finalizing record plans.