SERFM - Coopersville Main Lift Station

Important Information

Access/Traffic: During construction, Pin Oak Drive and access to all driveways will remain open. Residents will notice an increase in construction traffic, and there may be temporary restricted access near 320 Pin Oak Drive to protect residents and crews.

Contact

Prein&Newhof
Will Thies, PE
(616) 432-6715
wthies@preinnewhof.com

Contractor
Grand River Construction
(616) 669-5611

Muskegon County
(231) 724-3440

City of Coopersville
(616) 997-9731

  • The lift station was started up on August 17. Flow was diverted to West Randall Lift Station on August 18, and the station was considered substantially complete on August 19 after Windemuller corrected some controls and SCADA issues. The bypass pumps will be removed early next week.
  • We are compiling a punch list and finalizing record plans.

Work Completed:

  • Pumps and remaining valves and piping installed
  • Generator gas piping installed
  • Electrical wiring and SCADA programming continued

Upcoming Work:

  • Install control valve actuators
  • Complete electrical and instrumentation wiring and PLC/SCADA programming prior to startup
  • MCC startup is scheduled for August 10-11
  • Generator startup is scheduled for August 11-12
  • Live lift station startup is scheduled for August 12
    • On Monday or Tuesday (August 10 or 11), Main Lift Station bypass flows will be diverted away from the WWTP through the new 20-inch force main to West Randall Lift Station

Work Completed 

  • Generator set and wired
  • Pump bases poured
  • Valves and piping painted
  • Electrical conduit and wiring continued

Upcoming Work:

  • Set pumps and finish installing and testing final valves and piping
  • Install generator gas piping
  • Complete electrical and instrumentation wiring
  • Complete PLC and SCADA programming
  • Generator startup scheduled for August 3-4
  • MCC startup scheduled for August 10-11
  • Live lift station startup scheduled for August 12
    • Before live startup, flows will be diverted through the new 20-inch force main to West Randall Lift Station

Work Completed:

  • Demolition and wet well cores
  • Installation of control panel and MCC
  • Electrical conduit and wiring
  • Generator pad pour

Upcoming Work:

  • Generator will be set once pad achieves adequate strength
  • Pump bases will be poured and pumps set
  • Electrical conduit and wiring will continue
  • Process piping and valve installation will be completed
  • Startup is tentatively scheduled for the week of August 10

Work Completed:

  • Pumps, valves, piping, and electrical demolished
  • Yard piping installed and tested
  • Process piping, valves, conduit, interior equipment pads, and control panel installation started
  • Generator pad frost walls poured

Upcoming Work:

  • Generator pad pour
  • Pump base pours
  • Electrical conduit and MCC installation
  • Wet well cores and suction pipe installation
  • Bypass pump setup and testing is complete. The station will be removed from service early next week to begin demolition.
  • Process pipe installation is partially complete.
  • The force main yard piping and bypass connection will be installed tomorrow and next week.
  • All major equipment has been delivered except the control panel, which is 2-3 weeks out.
  • Bypass pumping is anticipated to begin the week of May 18, with demolition shortly after.