November 6, 2026
Pump Station 5
Work Completed:
- Upstream manhole cone replaced and raised (see photo)
Upcoming Work:
- Start bypass pumping
- Disconnect electrical service and demolish existing equipment
- Clean wet well
Traffic Control:
- Brower Lake Road will be closed on either side of the pump station starting next week
- All driveways will remain accessible
Pump Station 8
Work Completed:
- New piping and valves installed and tested
- Structure lids removed and replaced
- Pumps installed (see photo)
- Control panel conduit installed and equipment pad poured (see photo)
Upcoming Work:
- Install control panel, instrumentation, and wiring
- Backfill site and begin restoration
- Prepare for startup
Traffic Control:
- Bypass pumps have been relocated to the wet well, so the intersection of Hessler and Orlin has been reopened
- Construction traffic will still be present, so drive with caution