Progress Report:
Water main construction was completed along Walnut up to the Chestnut intersection this week. B&L started water main construction on the south end of Maple on Thursday.
Upcoming Work:
Next week B&L plans to finish the water main construction on Maple up to the Chestnut intersection. The next step will be to fill the new water main for testing.
Extra Notes:
In the coming weeks, B&L will begin contacting residents to coordinate lead service line replacements. If your house has an existing lead service line your water service will be replaced from the water main to the water meter in your house. Some water meters are in a meter pit out by the sidewalk. The water meter will be relocated inside the house as part of this project. B&L will be working with Tubergen Underground to complete the lead service line replacements and will need to gain access to the inside of your house to complete the work.
