Progress Report: We are making way for the construction of a new Water Treatment Plant located at 505 New York Avenue. The work so far has included removal of two residential structures. After removing the foundations, the site was graded to get ready for the new building.
Upcoming Work: This week, we will be working in New York Avenue to move electrical utilities and buried natural gas lines, which will include removal of some trees on the north side of the road. In a couple weeks, we will be installing temporary construction fencing and removing additional trees and brush on the south side of New York Avenue.