Progress Report:
This week the contractor has been working hard getting the gravel base ready for paving. The pavers will be onsite Friday, November 13 to start the base course, and hope to be done early next week.
In addition, work continues on the boardwalk and bridge.
Upcoming Work:
Next week they plan to complete paving and work on restoration.
The beams for the bridge are scheduled to be delivered early the week of Thanksgiving, and placed the next week. As soon as the beams are in, the special decking will be installed.