May 18, 2026
Construction of the Downtown Plaza continues with the completion of all underground work! Road rebuilding is well underway with the installation of curb on Main Street and State Street east of State St centerline.
Work Completed Last Week:
- Road rebuilding continues on Main St. and State St. with the installation of curb.
- Electrical conduit installed on Main St. and State St.
- Irrigation lines installed on Main St. and State St.
- Work has begun behind the curb with the installation of planter boxes and sidewalk grading.
Anticipated Work This Week:
- Grading behind the curb in preparation for the installation of sidewalks.
- Continue to pour concrete for planter boxes.