Progress Report:
Preparation of the bore pits continues by Lowe, the subcontractor completing the jack and bore under the box culvert near the pump station. The 42 inch casing will likely be installed this week. Consumers Energy is scheduled to relocate their power poles along Lakewood Blvd this week, in preparation for gravity sanitary sewer installation by K&R.