November 13, 2026
K&R continues to work towards reaching substantial completion. This week K&R completed concrete curb and sidewalk along 120th Ave. HMA paving of driveways and pathways along 120th Ave was completed this week as well. Top course paving is anticipated to be completed over the weekend. With restoration of road markings and traffic signals anticipated the week of November 16. Opening of 120th Ave from Lakewood Blvd through James Street is anticipated the week of November 16.
Road closure and traffic control on 120th Ave through the James Street intersection will remain in effect until work in the road is complete and the barricades are removed. We ask to continue following the above detour routes and to keep traffic to local businesses only.