Holland Charter Township - Lakewood Blvd & 120th Ave Sewer Improvement Project

Important Information

Holland Charter Township will be replacing/upsizing the wastewater trunk sewer from a pump station along Lakewood Blvd near US-31 to the east to 120th Avenue, and north on 120th Avenue to James Street.

The project will include lane closures, road closures/detouring, utility excavation/installation, pavement removals, and restoration activities.

Schedule: May – November, 2026

Access/Traffic:

  • Emergency vehicle access will be maintained.
  • Local resident access will be maintained and coordinated with the contractor.
  • There may be times where access will be limited to your residence/business during construction activities. Contractor to coordinate alternate parking locations may be needed for short periods.

Mail:
Temporary mailbox location may be installed. Contractor will coordinate with residents.

Garbage Pickup:
Contractor may request trash receptacles to be replaced at the road the night before.

Contact

P&N Engineer
Jonathan Nelson, PE, Project Manager
(616) 432-6741

P&N Construction Observer
Jesse Boogaard, Construction Observer
(616) 394-0200

Contractor
Kamminga & Roodvoets, Inc. (K&R)
Tim Brink, Project Manager
(616) 949-0800

Holland Charter Township
Aaron Nyboer, Director of Public Works
(616) 396-1891


Planned Lakewood Blvd Detour

Progress Report:

Preparation of the bore pits continues by Lowe, the subcontractor completing the jack and bore under the box culvert near the pump station. The 42 inch casing will likely be installed this week. Consumers Energy is scheduled to relocate their power poles along Lakewood Blvd this week, in preparation for gravity sanitary sewer installation by K&R.

Phase 1 of the project has begun with the closure of Lakewood Blvd the past Monday (May 4th). Westbound traffic is shifted to one lane, while eastbound traffic is detoured to US-31 & James Street. Milling of the southern three lanes was completed Tuesday. Material & equipment will continue to be delivered this week, in preparation for excavation to begin next week.