Holland Charter Township - Lakewood Blvd & 120th Ave Sewer Improvement Project

Important Information

Holland Charter Township will be replacing/upsizing the wastewater trunk sewer from a pump station along Lakewood Blvd near US-31 to the east to 120th Avenue, and north on 120th Avenue to James Street.

The project will include lane closures, road closures/detouring, utility excavation/installation, pavement removals, and restoration activities.

Schedule: May – November, 2026

Access/Traffic:

  • Emergency vehicle access will be maintained.
  • Local resident access will be maintained and coordinated with the contractor.
  • There may be times where access will be limited to your residence/business during construction activities. Contractor to coordinate alternate parking locations may be needed for short periods.

Mail:
Temporary mailbox location may be installed. Contractor will coordinate with residents.

Garbage Pickup:
Contractor may request trash receptacles to be replaced at the road the night before.

Contact

P&N Engineer
Jonathan Nelson, PE, Project Manager
(616) 432-6741

P&N Construction Observer
Jesse Boogaard, Construction Observer
(616) 394-0200

Contractor
Kamminga & Roodvoets, Inc. (K&R)
Tim Brink, Project Manager
(616) 949-0800

Holland Charter Township
Aaron Nyboer, Director of Public Works
(616) 396-1891

120th Ave Detour – Starting 09/21/2026:

K&R continues to work towards reaching substantial completion. This week K&R completed concrete curb and sidewalk along 120th Ave. HMA paving of driveways and pathways along 120th Ave was completed this week as well. Top course paving is anticipated to be completed over the weekend. With restoration of road markings and traffic signals anticipated the week of November 16. Opening of 120th Ave from Lakewood Blvd through James Street is anticipated the week of November 16.

Road closure and traffic control on 120th Ave through the James Street intersection will remain in effect until work in the road is complete and the barricades are removed. We ask to continue following the above detour routes and to keep traffic to local businesses only.

This week, base and level course paving were completed along 120th Avenue through the James Street intersection. Paving is anticipated to be completed late next week; the week of November 9. With road opening anticipated the following week; the week of November 16. Road closure and traffic control on 120th Avenue through the James Street intersection will remain in effect until work in the road is complete and the barricades are removed.

The Lakewood Blvd and 120th Ave Sewer Improvement Project is nearing completion. Earlier this week, the final sanitary improvements were installed. Abandonment and removal of the old system was completed.

K&R continues to build road and pour curb along 120th Ave. Paving is anticipated to begin the week of November 2 and end the week of November 9. Opening of 120th Ave from Lakewood Blvd through James Street is anticipated the week of November 16.

Progress Report:

K&R continues to lay 21-inch gravity sewer on 120th Ave heading north. The pipe crew has reached the James Street and 120th Ave intersection which is the final stage of the project. Once mainline is completed, efforts will continue towards testing, road building, paving, and restoration.

The pouring of curb on 120th Ave began late last week and will continue into this week. A road crew continues to build road on 120th Ave.

Progress Report:

K&R continues to make progress on 120th Ave with several crews focusing on gravity sewer, water main, and road rebuilding. The water main crew completed replacing and connecting to the existing water main in the James St and 120th Ave Intersection. The gravity sewer crew has resumed progress on installing 21-inch gravity sewer on 120th Ave after installing an additional method of dewatering. A road crew arrived late this week and began building road on 120th Ave starting at Lakewood Blvd heading north.

Progress Report:

K&R continues to make progress on laying 21-inch gravity sewer along 120th Ave towards James Street. A second crew began laying water main in the James Street and 120th Ave intersection earlier this week. The new water main is expected to be installed, tested, and connected to the existing system prior to laying gravity sewer in the intersection.

The James Street and 120th Ave intersection will remain closed the duration of the construction. Detour routes and local traffic access will remain in effect.

Progress Report:

K&R continues to lay 21-inch gravity sewer along 120th Ave heading north towards James Street.

Upcoming Work:

The closure of the James Street and 120th Ave intersection is scheduled for MONDAY, SEPTEMBER 21. See the map above for the respective detour routes. Local traffic will have access to their property for the duration of the closure.

Local traffic will have access as follows:

  • 120th Ave from Lakewood to James will have access from the south via Lakewood Blvd. 120th Ave from Lakewood to James will continue to have one northbound lane open from Lakewood Blvd to Garden Ave. Local Traffic will enter 120th from the south at Lakewood Blvd, head north on 120th and exit via Garden Ave back to Lakewood Blvd. Local traffic south of the James and 120th Intersection and north of Garden Ave will have access north of Garden Ave with two way traffic to enter in and out. The two way traffic zone will also be redirected to Garden Ave when exiting.
  • 120th Ave from Riley to James will have access from the north via Riley/Felch.
  • James street from US31 to 120th will have access from the west via US-31.
  • James Street from 112th to 120th will have access from the east via 112th.

Progress Report:

Lakewood Blvd is now open! Paving was completed on Thursday, and the Intersection was ready to open by Friday afternoon. K&R will continue restoration along Lakewood Blvd.

120th Ave will remain closed as K&R continues to lay 21-inch gravity sewer north towards James Street. A single northbound lane on 120th will remain open to give local traffic access from the south. See the above map for detour routes and local traffic access.

K&R has maintained two crews for work along 120th Ave and Lakewood Blvd. Along 120th a pipe crew continues to install 21-inch gravity sewer heading north towards James St. Along Lakewood Blvd, paving of the base and level course were completed last week. Driveway and top course paving are anticipated to be completed this week weather depending.

Progress Report:

K&R continues to lay 21-inch gravity sewer on 120th Ave heading north towards James Street. Restoration of Lakewood Blvd has begun with new curb and asphalt being installed. Restoration of Lakewood Blvd will continue throughout the next couple weeks. Road closure and traffic control on Lakewood Blvd will remain in effect until work in the road is complete and the barricades are removed.