Progress Report:
K&R continues to lay 21-inch gravity sewer on 120th Ave heading north towards James Street. Restoration of Lakewood Blvd has begun with new curb and asphalt being installed. Restoration of Lakewood Blvd will continue throughout the next couple weeks. Road closure and traffic control on Lakewood Blvd will remain in effect until work in the road is complete and the barricades are removed.