Progress Report
- Masons continued working on the west parapet wall, and a nice architectural feature was added above the west side of the tunnel
- Frontier Communications had a large team working to reinforce their infrastructure over the tunnel
- Structural crews continued to work on the footings for the retaining walls on the east side of the tunnel approaches
Upcoming Work Planned for the Next 4-6 Weeks:
- Next Week: Utility restoration over the tunnel for communication and gas lines should be completed, and road restoration may begin with gravel road base installation. Continue working on the footings for the east side retaining walls. Continue masonry on the west walls.
- Week of November 16: Road building of the east half of M-52, including concrete curb and gutter, road gravel base, and asphalt. Weather permitting, the east half of the road should be completed before Thanksgiving. Pouring concrete retaining walls. Begin pouring the path on the west side of M-52 towards the tunnel. Complete the masonry on the west walls; begin working on the east wall masonry.
- End of November/December: Complete pouring the concrete retaining walls on the east side and begin installing the modular block walls on the east side.
- Before Christmas: Pour path on east side, cleanup of site, lighting, furniture, interior tunnel work, and electrical work
- Spring 2027: Plantings and final restoration.
Recent photos from the construction site:




























