City of Adrian and Lenawee Now - S. Main Street Pedestrian Tunnel under M-52

Important Information

The Kiwanis Trail is an 8-mile Lenawee County trail, converted from a railroad to an asphalt and concrete surface ideal for biking, cross country skiing, in-line skating, walking, and running. The trail has been extended east along the Adrian and Blissfield railroad tracks and needs a safe crossing under M-52.

The tunnel will improve both safety and accessibility along the trail. Spanning 84 feet, its design draws inspiration from the nearby historic railway bridge built in 1867, incorporating stone veneer and steel bars. Additional features include benches, natural landscaping, LED lighting, and security cameras.

No local tax money is being used to fund this project. Lenawee Now provided funding for the design phase and assisted with grant procurement.

Tunnel location

Contact

Project Manager and Designer
Prein&Newhof, Grand Rapids, MI
Dan Sorek, PE
(616) 218-2940 – Cell
dsorek@preinnewhof.com

On-site Engineer and Construction Inspection
Mannik & Smith Group, Adrian, MI
Justin Kirkpatrick
(734) 770-5425 – Cell

General Contractor
Dunigan Brothers, Jackson, MI
Superintendent (24-Hour Emergency Contact) – Drake Dunigan
(517) 936-9132
drake@duniganbros.com

Progress Report

  • Excavation is complete for the installation of the footings on the west side
  • MILESTONE: First concrete pours for wall footings took place this week. This is the deepest work, and work will now begin upward!
  • Underdrain and storm drain under the new tunnel was installed on the west side

Upcoming Work Planned for Next Few Weeks:

  • Reinforcing steel will be placed and footings will be poured for the wingwalls
  • Additional underdrains will be installed
  • Additional preparations will be
First pour of concrete for the bottom of the west wing wall footings

 

Crews forming up for the next foundation pour next week

 

Crews removing forms from the footings

Progress Report

  • Earthwork has gone as far as possible on the east side of M-52 until we can build hard walls
  • Excavation continued to prepare the site for foundations to be poured for the walls on the west side
  • Restoration efforts continued on the far west side

Upcoming Work Planned for Next Few Weeks:

  • Foundations will be poured for the wingwalls of the tunnel
  • Underdrains will be installed
  • Additional preparations will be made for installing the tunnel sections in a few weeks
Seeding and restoration have taken place on the far west side of the construction site

 

The view of the tunnel approach from S Main Street

Construction continued this week on the Adrian Pedestrian Tunnel under M-52, South Main Street. Here is a quick update.

Progress Report

  • Earthwork continued on the east side of M-52 with excavation for the new path to the tunnel
  • Steel sheets were installed in preparation of pouring footings for the west wing walls
  • Topsoil was spread, and some restoration efforts began on the west side

Upcoming Work Planned for Next Few Weeks:

  • Foundations will be poured for the wingwalls of the tunnel
  • Underdrains will be installed
  • Additional preparations will be made for installing the tunnel sections in a few weeks

Recent construction site photos from Mannik Smith Group:

Crews installing the temporary sheet piles in M-52, preparing for the west wing wall

 

Looking east from the west side of M-52 where the west wing walls will be installed soon

 

Crews spreading topsoil on the west side for restoration

Construction resumed this week on the Adrian Pedestrian Tunnel under M-52, South Main Street. Here is the latest update.

Progress Report

  • Earthwork has begun on the east side of M-52 with excavation for the new path to the tunnel
  • Steel sheets were delivered to the site, and preparations were made for installation before the installation of the west side wingwall footings and foundations

Upcoming Work Planned for Next Few Weeks:

  • Continued earthwork on the east side of the tunnel
  • Sheet piling will be installed on the west side
  • Foundations will be poured for the wingwalls of the tunnel
  • Underdrains will be installed
  • Additional preparations will be made for installing the tunnel sections in a few weeks

Recent construction site photos:

Excavation on the east side for the path towards the tunnel has started

 

Looking east from M-52 towards the path leading down to the tunnel

 

A reminder that the path is closed for construction, but not everyone follows construction signs

The wet spring put a damper on the construction of the tunnel. However, work will resume next week, Monday, May 11, 2026.

Progress Report

  • No progress has been made for the last 2-3 weeks due to the wet conditions.

Upcoming Work Planned for Next Few Weeks:

  • Earthwork will take place on the east side of the tunnel with topsoil stripping and excavation in preparation for the tunnel and walls on the east side of the road
  • Sheet piling will be installed around the trench where the tunnel sections will be set safely for the crews
  • Foundations will be poured for the wingwalls of the tunnel
  • Underdrains will be installed
  • Additional preparations will be made for installing the tunnel sections in a few weeks

Traffic shift still in place:

Like the rest of Michigan, this spring’s rain and weather have made an impact on our Adrian Pedestrian Tunnel. The site was just too wet to install sections of the tunnel this week.

Progress Report

  • The water main is relocated and in service around the new tunnel
  • Drainage system is installed up to the base of the tunnel
  • Communication lines have been spliced and are prepared for relocation

Upcoming Work Planned for Next Few Weeks:

  • Sheet piling will be installed around the trench where the tunnel sections will be set safely for the crews
  • Foundations will be poured for the wingwalls of the tunnel
  • Underdrains will be installed
  • Additional preparations will be made for installing the tunnel sections in a few weeks

Traffic shift in place:

 

Looking south where the tunnel will be installed under the road:

 

Looking east at the future tunnel site under M-52/South Main Street:

Progress on the Adrian Pedestrian Tunnel is moving forward and next week will see the first sections of the tunnel getting set.

Progress Report

  • Relocated water main has been tested for connection to the existing system
  • The west half of the road pavement of South Main Street/M-52 was removed
  • Excavation continues for the tunnel and west walls
  • Utility relocation coordination continues – splicing of communication lines in preparation of relocation is ongoing
  • Additional construction materials and pipe were delivered to the site, including forms for the west walls

Upcoming Work Planned for Next Few Weeks:

  • Water main tie-ins are planned for Monday, April 13, 2026. Affected customers have been or will be notified between Merrick and Crystal Spring. Water should only be off for a couple of hours on Monday before it is restored in the afternoon.
  • Communication cable splicing will continue for the relocation of phone lines on the east side of M-52
  • The first sections of the precast tunnel are tentatively scheduled to be set on Tuesday, April 14, 2026!

Traffic shift in place:

 

Photo from the site this week from Mannik & Smith Group:

Crews removed the pavement on the west half of M-52-S Main Street

Progress on the Adrian Pedestrian Tunnel will certainly be picking up steam after Spring Break and the Easter Holiday.

Progress Report

  • Drainage system is installed up to the base of the tunnel
  • Traffic shift and lane reductions were put in place this week
  • The relocated water main pipe has been installed and is in the testing phase before connecting it to the system
  • Excavation has begun for the tunnel and walls
  • Utility relocation coordination continues – splicing of communication lines in preparation of relocation is ongoing
  • Additional construction materials and pipe were delivered to the site

Upcoming Work Planned for Next Few Weeks:

  • Water main relocation should be completed next week – Disruptions to drinking water may occur at the end of the week for tie-ins to the existing system. This will affect residents for a few hours during the day on M-52 between Crystal Spring Avenue and Merrick Street.
  • Communication cable splicing will continue for the relocation of phone lines on the east side of M-52
  • The first section of the precast tunnel could be delivered and installed late next week!

Traffic shift in place:

Photos from the site this week from Mannik & Smith Group:

Excavation for the tunnel sections has begun

 

Crews finishing the water main work

 

Excavation for tunnel sections in relation to the current road, which will begin to be removed soon

Progress may seem slow now, but the pedestrian tunnel construction in Adrian is picking up momentum. The project remains on schedule.

Progress Report

  • Drainage installation continued up to the base of the tunnel with pipe and new structures installed
  • Water main relocation began
  • Utility relocation coordination continues
  • Additional construction materials and pipe were delivered to the site

Upcoming Work Planned for Next Few Weeks:

  • Water main relocation should be completed next week – Disruptions to drinking water may occur at the end of the week for tie-ins to the existing system. This will affect residents for a few hours during the day on M-52 between Crystal Spring Avenue and Merrick Street.
  • Traffic shifts will take place next week – reminder with map shown again – tentatively planned for March 31, 2026
  • Traffic will be impacted with lane shifts on M-52
    • Traffic at the tunnel location will be reduced to one lane in each direction, with all traffic getting shifted to the current northbound lanes.  This will only be between the Railroad crossing and Cross Street. M-52 will remain open to all traffic, just reduced to one lane in each direction and shifted to the east side of the road.
  • Communication cable splicing will begin in preparation for the relocation of phone lines on the east side of M-52
  • The first section of the precast tunnel will be delivered and installed around the first full week of April

Photo from the site this week from Mannik & Smith Group:

Crews are finishing the drainage system piping before turning to work on the water main relocation

Construction on the Adrian Pedestrian Tunnel had some slow, but steady and safe progress this week. The project remains on schedule.

Progress Report

  • Drainage pipe installation continued from the outlet up towards the base of the tunnel
  • Coordination with other utilities for any potential conflicts with construction
  • More materials delivered to the site

Upcoming Work Planned for Next Few Weeks:

  • Complete storm sewer installation up to the tunnel, including backfilling over the new storm sewer
  • Water main relocation will begin later in the week of March 23
  • Traffic shifts that we warned about last week will likely take place later next week – reminder with map shown again – tentatively planned for March 25, 2026
  • Traffic will be impacted with lane shifts on M-52
    • Traffic at the tunnel location will be reduced to one lane in each direction, with all traffic getting shifted to the current northbound lanes.  This will only be between the Railroad crossing and Cross Street. M-52 will remain open to all traffic, just reduced to one lane in each direction and shifted to the east side of the road.
  • Communication cable splicing will begin in preparation for the relocation of phone lines on the east side of M-52
  • The first section of the precast tunnel will be delivered and installed around the first week of April

Traffic shift to occur later next week:

 

Rebar delivered to the site for the reinforced concrete walls to be built

 

Crews working to finish the drainage system