November 13, 2026
Progress Report
- Masons continued working on the west parapet wall.
- Frontier Communications completed securing their lines over the tunnel
- Backfill over the tunnel and gravel road base was placed. Preparations for concrete curb and gutter were made.
- Storm drains were installed on the east side of M-52 and reconnected.
- East side footings were poured at for the retaining walls for the tunnel approach
Upcoming Work Planned for the Next 4-6 Weeks:
- Next Week: Concrete curb and gutter will be poured on the east side of M-52. The gravel road base material will be compacted, shaped, and made ready for asphalt paving. The goal is to place all layers of asphalt and have all lanes ready for re-opening by the end of the week. Gas main will be reconnected over the tunnel. Masons will continue their stonework on the west wall, and the structural team will continue building the east side retaining wall on the south side.
- Week of November 23: Thanksgiving week. No work will take place later in the week, but there will be work on the retaining wall and backfilling over the tunnel. Masons will continue working.
- End of November/December: Pour concrete path on the west side of the tunnel. Complete pouring the concrete retaining walls on the east side and begin installing the modular block walls on the east side.
- Before Christmas: Pour path on east side, cleanup of site, lighting, furniture, interior tunnel work, and electrical work
- Spring 2027: Plantings and final restoration.
Fiber lines encased in concrete and crews installing new storm drains for the east side of M-52
A lot of fiber optic and other communication lines are safely protected and awaiting concrete encasement
A view of the masonry on the west side parapet wall
Crews pouring the structural footings for the east side retaining walls
The east side of M-52 with gravel road base, getting ready for new curb and gutter next week:
























