Quail Crest Condo Association

Important Information

Project Schedule Update:

Tuesday 9/8
Top Course Driveways, Speed Bumps and Grouse Ct/S Quail Crest Dr
Rieth-Riley Construction

Wednesday 9/9
Pavement Markings/Signs
Industrial Commercial Striping

Thursday 9/10
Top Soil/Restoration
Youngstrom

Friday 9/11
Remove Traffic Control
Rieth-Riley Construction

Unfortunately, the contractors were unable to do the final paving today. They will be on site tomorrow to pave Grouse Ct, the speed humps and the driveways that were removed. Thank you again for your patience.

The contractor is still working on the drives and Grouse Ct to get them ready for asphalt paving.  Reith Riley will also be on site today to prep the areas for speed bumps.  If all goes as planned today, final paving will take place tomorrow.  Thank you for your continued patience.

Quick schedule update after yesterday’s mishap on Grouse Court:

Thursday 8/27
Complete undercut/subgrade repair on Grouse Court

Thurs-Friday 8/27-28
Remove two driveways in Phase 2 Blue Section (5073 Quail Crest Drrive & 2283/2282 Partridge). Need to be flexible as we hope to complete these with top course tomorrow. Most likely will be removed tomorrow morning (8/28)

Friday 8/28
Base course Grouse Court, base & top course two driveways, top course Phase 2 (Blue Section)

Monday 8/31 
Remove HMA in remainder of the driveways/add gravel/fine grade

Tuesday 9/1
Base/top driveways
Top Grouse Court and Quail Crest to Burton Street
Install speed bumps

Wednesday 9/2
Restoration

Thursday 9/3
Pavement markings

Thank you for your continued patience as we improve some of the streets at Quail Crest.  The following is the updated schedule for the remainder of the project.  This schedule is weather dependent.

 

Updated schedule:

8/24 Monday – Milling blue phase streets and removing asphalt drives per contract

8/25 Tuesday – Place base course of asphalt on blue phase streets and drives

8/26 Wednesday – Excavate and install gravel on Grouse Ct and adjust manholes in the blue section

8/27 Thursday – Complete excavation and gravel work on Grouse Ct

8/28 Friday – Pave base course of asphalt on Grouse Ct and pave top course all remaining street sections and drives

8/31 Prep and install speed bumps

9/1  Install pavement markings

As you can see, the contractor made great progress (mostly) as planned this week on the road project.  Feel free to drive on the roads in phase 1 as needed.  However, please avoid parking on the edges of the new pavement for the next week to allow the valley gutters time to cure.  This will help avoid damaging this part of the pavement.

The contractors ran into some unforeseen conditions on Grouse Ct. that have delayed that part of the project as well as the final top course of asphalt to the east of Grouse Ct.  The contractors will be back next Monday to remove driveways and start milling the pavement in phase 2.  The work on Grouse Ct. is still being scheduled.  Stay tuned for further updates.  Thank you for your continued patience.

Construction is expected to start next Monday, August 10 on the streets shown on the map.  The red streets will be done as Phase 1 and then the blue streets will follow.  In addition, the driveways to 2282 & 2283 Partridge Ct (shared driveway), 4899 North Quail Crest, 4915 North Quail Crest, 2270 South Thrush Ct, and 5073 South Quail Crest will be done as part of Phase 2.  Also, 4 speed humps will be placed at the end of Phase 2.

Phase 1  (units affected: 4811 – 4834 NQC, all Teal Ct, 4916 – 5069 SQC, all Grouse Ct, 5135 Burton)

Date/DayRoad/TrafficActivityContractor
August 10         MNo impactSet up Traffic Control/Staking/SESCRieth-Riley
August 10         MBurton entrance closedRemove and Replace Curb and GutterYoungstrom
August 10-11  M-TuSingle lane closureLower ManholesYoungstrom
August 12         WSingle lane closureMill Red SectionJL Milling
August 12-13  W-ThSingle lane closureProof Roll/Undercuts/GradingYoungstrom
August 14         FSingle lane closure, expect delaysHMA Base CourseRieth-Riley
August 15-17  Sa-MSingle lane closureRaise ManholesYoungstrom
August 18         TuRoad closed, limit use as much as possibleHMA Top CourseRieth-Riley

 

Phase 2  (units affected: 5073 – 5145 SQC, all Bobwhite Ct, all Partridge Ct, all Pheasant Ct)
[driveways: 2282 & 2283 Partridge Ct (shared), 4899 NQC, 4915 NQC , 2270 S Thrush Ct, 5073 SQC]

Date/DayRoad/TrafficActivityContractor
August 19         WNo impactSet up Traffic Control/Staking/SESCRieth-Riley
August 19         WSpaulding Ave entrance closedRemove and Replace Curb and GutterYoungstrom
August 19         WSingle lane closureLower ManholesYoungstrom
August 19-24  W-MDriveway closureRemove & Grade HMA DrivewaysYoungstrom
August 24         MSingle lane closureMill Blue SectionJL Milling
August 24         MSingle lane closurePrep Phase 2 & cut Butt Joints/Speed BumpsRieth-Riley
August 25         TuSingle lane closureHMA Base Course/Driveways/Speed BumpsRieth-Riley
August 26         WSingle lane closureRaise ManholesYoungstrom
August 27         ThRoad closed, limit use as much as possibleHMA Top Course/DrivewaysRieth-Riley
Aug 28-Sep 5  F/SaMinimal impactTurf RestorationYoungstrom
September 8  TuMinimal impactPavement Markings/SignsICS
September 9  WMinimal impactRemove Traffic ControlRieth-Riley

 

  • The Burton St. entrance will be closed from August 10 to August 17.
  • The irrigation system will be shut off by the Association prior to paving the top course of asphalt.
  • The driveways that are being replaced will be removed on or about August 19.
  • Please avoid parking on the new asphalt for approximately 2 days and especially on the edges to avoid damaging your new road.
  • Parking at the clubhouse will not be permitted on days that milling or paving is scheduled.  Currently, those days are August 12, 14 and 18.
  • Please be patient while the project is going on and do you best to avoid unnecessarily driving through the active construction area.