Work Completed this past week (June 9-14)
- C1, Sanitary sewer installed on Red Bud from Dewey to 3rd Street.
- C3, Water main pipe installation completed on Front Street, East of Days Ave.
- C3, pavement removals completed on Front Street from Days to Oak Street.
- Milling/Paving of Liberty Street/Rynearson Street on Friday (6/13) and Saturday (6/14). Reith Riley will flag traffic and not need to shift the detour.
- Retaining wall work complete, Front Street opened to traffic to Johnson Street. Front Street closed from Oak to Red Bud.
- Culvert work behind Library is complete.
Work planned for this week (June 16-20)
- C1, continue sanitary sewer install at Red Bud South of Dewey.
- C1, continue storm sewer install on 3rd Street (second crew coming in, traffic will still be able to use 3rd Street for access).
- C3, continue water main install on Front Street, West of Days Ave.
- C3, begin testing water main pipe on Front Street East of Days.
- Front/Oak Street intersection planned for closure Monday (6/23) for water main install.