May 14, 2025
Pump Station: The wetwell walls have been poured and the forms were removed Monday (12th). Testing will need to be completed on the wetwell (leakage, concrete strength, etc) in the future. The wetwell lid is being prepped for construction. Once testing is complete, the trench box rail system will be removed and the outside of the wetwell will be backfilled/compacted.
Force Main: Installation of the 30-inch force main along River Hills Drive has progressed. K&R completed the ZBPW transmission main crossing at Scotts Drive last week successfully (see below pictures). K&R is preparing to pressure test a section of FM pipe and then start restoration at the Macatawa Bank property.
Future Schedule (Tentative): Beeline Road Closure: June 2, 2025