November 20, 2026
Progress Report
- Masons nearly completed their work on the west side and will soon move to the east side.
- Citizens Gas completed the gas main replacement over the tunnel.
- Concrete curb and gutter have been installed, and the east half of M-52 is getting paved today. The west half will have the final course of asphalt installed next Monday, November 23. Periodic lane closures may still be required, but only the outside lanes will be closed if needed.
- The concrete seat wall was poured on the east side, and steel and formwork were done for the south retaining wall on the east side.
Upcoming Work Planned for the Next 4-6 Weeks:
- Next Week (short week due to Thanksgiving): The remainder of M-52 will be paved. Temporary pavement markings will be installed. The south concrete retaining wall will be poured. Masons will continue adding stone to the parapet walls and above the tunnel.
- Week of November 30: Backfilling behind the walls will take place. A gas service to the gas station will be replaced. Excavation for additional wall footings will take place and possibly be poured. Railings on the west side should begin to be installed. Concrete sidewalks along M-52 will be prepared and possibly poured.
- Early to mid-December: Continue building the poured concrete retaining wall. Masons should complete their work. Concrete path on the west side will be installed down to the trail. Modular block walls on the east side will begin. Poured concrete walls should be finished the week of December 14.
- After Christmas: Complete modular block walls on the east side. Install electrical, lighting, and security cameras. Pour concrete path down to the trail on the east side.
- Early Spring 2027: Final cleanup, coatings, furniture, plantings and landscaping, and grand opening!