City of Muskegon - Oakview and Sheldon Park Service Line Replacements

Important Information

The City will be replacing water services throughout the Oakview and Sheldon Park neighborhoods. This work will begin during the fall of 2024 and is anticipated to be completed by fall of 2027. Work will consist of replacement of all galvanized water services from the water main into the home.

Work will be completed by Gustafson HDD of Whitehall, MI. Gustafson will be reaching out to property owners to schedule replacement work as the project progresses.

Water Service: Water service will be interrupted for individual property’s as their service is worked on. Prior notice will be provided.

Contact

P&N Engineer
Matt Hulst
Project Engineer
231-798-0101

Contractor
Gustafson HDD
231-981-1025

City of Muskegon
Todd Myers
231-724-4100

There are currently no construction updates available for this project.