Work Completed this past week (April 21-25)
- Completed water main testing on 3rd Street in front of Red Bud Fitness.
- Performed startup/first tests on dewatering treatment unit.
- New soil samples taken from sanitary sewer trench on 3rd Street for testing.
- Started water service installs on Red Bud.
- Front Street Closed (Eastbound lane only) between Liberty and Rynearson for Retaining Wall repair (not part of Infrastructure project).
Work planned for this week (April 28 – May 2)
- Continue sanitary sewer install on 3rd Street.
- Continue water service install on Red Bud, Dewer, and Main Street.
- City Services to install Inserta-Valves Monday.
- Perform water main tie in on 3rd Street (in front of Red Bud Fitness) Monday at 4:30 pm until 8:00 pm.
- Flow sensor calibration on new flume scheduled for Wednesday (4/30).