Work Completed this past week (Sept 29 – Oct 3)
- C1, completed storm sewer and sanitary lateral install on Red Bud North of 3rd.
- C1, poured curb/gutter on Dewey and 3rd Street.
- C1, continued grading for sidewalk on Red Bud.
- C1, power poles removed at Red Bud/3rd Street.
- C1, Day Care and City Hall parking lot graded and prepped for paving.
- C3, completed storm sewer install on Front Street.
- C3, continued street light install on Front Street.
- C3, sand/gravel placed on Front Street from Days to Main Street.
Work planned for this week (Oct 6-11)
- C1, continue storm sewer install on Main Street between Front and Dewey.
- C1, anticipated paving date Oct. 10th.
- C3, pour curb/gutter on Front Steet Oct. 9th.
- C3, continue installing street light foundations/conduit on Front Street.
- C3, continue road building/prepping for sidewalk on Front Street from Days to Oak Street.