Work Completed this past week (April 7-11)
- Completed water main install on Main Street, ready for testing.
- Continued sanitary sewer install on 3rd Street.
- 3rd Street to remain closed at Skyline, Red Bud Fitness/City Hall to continue using 3rd/Red Bud intersection for access.
- Front Street Closed (Eastbound lane only) between Liberty and Rynearson for Retaining Wall repair (not part of Infrastructure project).
Work planned for this week (April 14-18)
- Continue sanitary sewer install on 3rd Street.
- Begin testing installed water main on Red Bud/Dewey/3rd/Main St. Water services to begin week after water main testing complete.
- Milling remaining asphalt on Red Bud and Main Street, est. Thur (4/17) and Fri (4/18). Brick removal on Main St. to begin shortly after.