- The new water main is installed in Broadway between Glade and Temple. Customers are connected to the new water main in this location, and it is tied to the existing system and in service.
- The new water main is installed in Broadway between 9th Street and 5th Street with connections to the existing system at 6th Street, 7th Street, and 8th Street. Customers are being connected to the new water main between 9th and 5th Streets.
- Storm drains are being replaced between Glade and Temple.
- Traffic control and preparations are being made for water main work on Delano Avenue between Reynolds and Getty Streets
The posted detour for Broadway Avenue is Glade Street to Summit Avenue to Peck Street back to Broadway.
The posted detour for Delano Avenue is Reynolds Street to Hackley Avenue to Getty Street
Upcoming Work Planned for Next Few Weeks:
- Water mains will be tied in at Broadway and 9th Street on Monday, April 20, 2026. This will mean a temporary water disruption for all customers on 9th Street between Summit and Sherman between 8 AM and 4 PM. Water should be turned back on before the end of the day. If the water is cloudy, that is air trapped in the lines. Please be sure to flush all of your water fixtures and clean the aerators on your faucets. It is best to flush the Cold water in a bathtub first because there is typically no aerator there, and it will move the most water. Be sure to remember to flush outside spigots as well now that the weather is improving.
- Sanitary sewer manholes will be replaced in the intersections of Broadway between 9th and 5th Streets
- Additional water main work will occur on 6th Street between Summit and Sherman, with 2 new hydrants and some water connections to eliminate an old water main on 6th Street
- Storm drain work will take place on Broadway between 9th and 5th Streets
- Water service lines will be replaced between 8th and 5th Street
- Roadway will begin to be shaped on Broadway between Temple and Glade Streets
- Water service replacements are happening all over the City as part of the Lead Service Line Replacement program
- Pavement removals for water main work on Delano between Reynolds and Ray Streets
- Water main work will begin on Delano Avenue between Reynolds and Ray Streets with the connections to the large water main in the alleys and installation of new hydrants and valves