Van Buren Street from Butternut to 160thAvenue is closed, from 160th to 152nd Avenue is closed, and from 152nd to 144th is closed.
Pipe laying has halted for the time being. K&R is continuing miscellaneous external and internal work on pipe already installed.
The first course of asphalt paving between Butternut and 160th Avenue is tentatively scheduled for the week of May 11, weather permitting. Restoration and road building along this length of road will begin soon as weather permits.
Van Buren Street from US-31 to 120thAvenue is closed.
Pipe laying continued eastward as weather conditions allowed. Pipe laying will continue next week as well as work inside the pipe.
New Holland Street from 104thAvenue to 96th Avenue is closed.
Ric-Man continues working on the pipe interior in preparation for pressure testing. Filling of the pipeline is expected to begin today.
Next week, Ric-Man will fill the remaining pipeline and pressure test, then begin connections to the existing pipeline in New Holland Street.