Van Buren Street from Butternut to 160thAvenue is closed, from 160th to 152nd Avenue is closed, and from 152nd to 144th is closed.
Road building began between Butternut and 160th The road is being graded for gravel placement.
K&R continues spot excavations to address some joint issues on the pipe already installed.
Next week, K&R plans to continue road building and recommence pipe laying east of Quail Meadow Court.
In the coming weeks, K&R will be relocating the pipe crew currently working east of US-31. The crew will begin pipe laying work between 144th and 136th Preparations for this work, including road removal, mailbox relocation, pipe staging, etc. are scheduled to begin the week of May 4. Property owners along this stretch of road should receive the letter soon.
Van Buren Street from US-31 to 120thAvenue is closed.
Pipe laying continued eastward. Pipe laying will continue next week as well as work inside the pipe.
New Holland Street from 104thAvenue to 96th Avenue is closed.
Ric-Man completed a pressure test of the pipe installed in New Holland Street and the easement piping to the south.
Next, Ric-Man will begin the process of connecting to the existing pipeline in New Holland Street and returning the 54″ transmission main to service.