Work completed/in progress:
- Dry well drains and formwork were installed in preparation for pouring the dry well floor.
- Electrical conduit installation began in the dry well.
Anticipated work activities for the coming week:
- The dry well floor will be poured Monday.
- Conduit installation will continue, and the masonry crew will begin mobilizing to construct the building walls.