Progress Report:

Riverworks mobilized on site Monday and began pile driving for the boardwalk near the intersection of Cannonsburg Road and Bear Creek Trail on Thursday. Terracon continued gravel placement along the path this week and addressed areas that were washed out from recent weather.

Upcoming Work:

Next week Riverworks plans to resume pile driving. Terracon will continue gravel placement and grading along the corridor. Integrity Landscaping is also expected on site early in the week to begin construction of the first retaining wall near the start of the path.

Note:

Thanks for your patience and attention to speed and our site workers as safety is everyone’s responsibility!