Progress Report
- Delano Avenue: The road is fully open to traffic. Only punch list items remain.
- Sanford Street: The final course of asphalt was installed, and lawn restoration took place.
- Oakwood Avenue: Grading for pavement restoration began
- Amsterdam Avenue: Utility pole relocation and water service work was done
- Getty Tank: Priming and painting of the tank continues. Roughly 65% of the work is complete now. Additional coats of paint will be done on the exterior.
- Over 75 lead water service lines were removed this past week again
Upcoming Work Planned for Next Few Weeks:
- Water service replacements are happening all over the City as part of the Lead Service Line Replacement program.
- Sanford: Final restoration, new signs, and punch list work.
- Oakwood: Concrete curb and gutter, road gravel, and road restoration
- Amsterdam: Sanitary sewer manholes will be replaced in the intersections of Glendale, Jefferson, and 5th Street. New storm drains will be installed.
- Getty Tank: Additional coats of paint will be done, interior work will be done, and new fencing and gates will be installed