Van Buren – Butternut to US-31
- Van Buren from Butternut to US-31 is closed.
- 144th Ave is scheduled to be re-paved today.
- 164th Ave is closed between New Holland and Van Buren.
- The final layer of asphalt on driveways between Butternut and 152nd is scheduled to be placed on August 25.
- The first layer of asphalt is scheduled to be placed between 152nd Ave and 136th Ave next week.
- Work on miscellaneous transmission main items will continue next week.
- Work inside the pipe continues.
164th – New Holland to Van Buren
- Pipe staging occurred this week and will continue next week.
Van Buren – US-31 to 96th Avenue
- Van Buren from US-31 to 120th Ave is closed.
- Preparations for the tunneling beneath US-31 and the Railroad continued. The tunneling operation is scheduled to begin today and will continue next week.
- The pipe crew began installation of the valve vault east of 128th Avenue.
New Holland – 104th to 96th & Easement
- New Holland Street from 104th Ave to 96th Ave is closed.
- New Holland Street paving began August 19 and should be completed today.
- Work continued on pipe appurtenances along Barry Street.