Thank you for your continued patience as we improve some of the streets at Quail Crest. The following is the updated schedule for the remainder of the project. This schedule is weather dependent.
Updated schedule:
8/24 Monday – Milling blue phase streets and removing asphalt drives per contract
8/25 Tuesday – Place base course of asphalt on blue phase streets and drives
8/26 Wednesday – Excavate and install gravel on Grouse Ct and adjust manholes in the blue section
8/27 Thursday – Complete excavation and gravel work on Grouse Ct
8/28 Friday – Pave base course of asphalt on Grouse Ct and pave top course all remaining street sections and drives
8/31 Prep and install speed bumps
9/1 Install pavement markings