This Week:
- Milbocker completed water main installation along Miramar between Eldon and Plainfield.
- The two water main connections at Audley were completed on Thursday.
- Two water services along Airway, west of Miramar, were replaced.
- Milbocker continued to prepare for sidewalk and driveway replacement north of Eldon. The concrete contractor was scheduled for earlier this week but is experiencing some delays.
- Milbocker began the process of filling the new water main and testing it this week.
- Storm sewer at the northern Daylor intersection was completed today.
Next Week:
- Milbocker will complete the Airway connection on Monday. Airway will be closed to thru traffic at Miramar and a detour route will be posted. The road will not be closed until 9:00 AM to allow the morning bus traffic to pass through. The goal is to have the road backfilled and repaved by the end of the day Monday.
- Water services will be installed south of Eldon pending passing test results later next week.
- Concrete work should be in full swing north of Eldon next week.