Progress Report
- Crews completed additional underdrain for the tunnel on the east side of the tunnel
- Shoring, bracing, excavation, and preparation was done for the east side footings to be installed
Upcoming Work Planned for the Next Few Weeks:
- Installation of east wall footings
- Construction of the east poured-in-place concrete walls
- Completion of the modular block walls on the west side
- Masonry on the west parapet wall and around the west tunnel face
- Grading and restoration on the west side
Recent construction photo from the site: