Work Completed:

  • Pumps and remaining valves and piping installed
  • Generator gas piping installed
  • Electrical wiring and SCADA programming continued

Upcoming Work:

  • Install control valve actuators
  • Complete electrical and instrumentation wiring and PLC/SCADA programming prior to startup
  • MCC startup is scheduled for August 10-11
  • Generator startup is scheduled for August 11-12
  • Live lift station startup is scheduled for August 12
    • On Monday or Tuesday (August 10 or 11), Main Lift Station bypass flows will be diverted away from the WWTP through the new 20-inch force main to West Randall Lift Station