Work Completed:
- Pumps and remaining valves and piping installed
- Generator gas piping installed
- Electrical wiring and SCADA programming continued
Upcoming Work:
- Install control valve actuators
- Complete electrical and instrumentation wiring and PLC/SCADA programming prior to startup
- MCC startup is scheduled for August 10-11
- Generator startup is scheduled for August 11-12
- Live lift station startup is scheduled for August 12
- On Monday or Tuesday (August 10 or 11), Main Lift Station bypass flows will be diverted away from the WWTP through the new 20-inch force main to West Randall Lift Station