** No road closures currently***
Work completed/in progress:
- Force main has been pressure tested, and structures have been installed.
- Restoration complete along Heights Ravenna Rd.
Anticipated work activities for the coming week:
- Jackson-Merkey will be offsite until September, when lift station construction will begin.
- Jackson-Merkey will continue watering new grass seed