Work Completed this past week (Feb 10-14)
- Digital PCMS boards have started arriving in town. These are positioned at the far East & West on Front Street, North & South on Red Bud Trail, and NE on River Street.
- USDA sign was installed in park at the NE corner of Front/Red Bud. This sign will be viewable from both the street and park.
- MISS DIG began working on clearing the detour route sign locations.
- Removal limits marked project wide.
Work planned for this week (Feb 17-21)
- Detour Route signs will begin to be installed.
- Tree removals planned to begin project wide week of Feb. 24. This includes 19 smaller trees on Front Street. We anticipate traffic on Front Street to remain open during tree removals.
- On March 3, the contractor plans to begin pulverizing roads, turning them to gravel. Contractor will smooth roads as work progresses, but you will see temporary lanes closures project-wide. We will coordinate with the contractor to find their specific schedule.