Work completed/in progress:
- Installed force main adjacent to Sullivan Lift Station.
- Continued force main installation south of Apple Avenue on MCRRC property.
Anticipated work activities for the coming week:
- Continue force main installation north of Apple Avenue. Install force main along southern end of the storage lagoon.
- Continue force main installation south of Apple Avenue. Complete crossing of the Muskegon-Newaygo Branch Drain and continue south