Work completed/in progress:
- Completed force main installation along Railroad corridor on north side of Continental property progressing toward 68th Avenue.
Anticipated work activities for the coming week:
- Cross 68th Avenue and continue force main installation along Railroad corridor.
- Prepare for first pressure test of force main.