Work Completed this past week (Feb 17-21)
- Project detour route signs have begun to be displayed. This detour route will remain active during the entire project.
- Continued speaking with business owners about upcoming construction start dates. Please forward anyone who has questions/concerns to me and I will touch base with them.
- Survey crew onsite staking tree removal limits/sanitary sewer at the WWTP.
Work planned for this week (Feb 24-28)
- Detour Route signs will continue to be installed.
- Front Street will be closed Monday (2/24) and Tuesday (2/25) for tree removals. Front Street will open back up to traffic once tree removal is complete. See picture below for Front Street closure.
- Tree removals will continue throughout the week on 3rd Street and Dewey. This work will only require small 1 block road closures.
- Construction of flume at WWTP will begin on Monday (2/24).
- Tentative start date – March 3rd the contractor plans to begin pulverizing roads, turning them to gravel. Contractor will smooth roads as work progresses but you will see temporary lanes closures project wide. Start of pulverizing depends on frost thickness in roads.